RECONSTRUCTION MOTOL UNIVERSITY HOSPITAL, PRAGUE

Customer
University Hospital Motol
Architect
Association Domy - OBERMEYER HELIKA a.s.
Main building designer
Association Domy - OBERMEYER HELIKA a.s.
Construction Period
2004 - 2018
Project realisation
2004 - 2018
Activities undertaken
surveys, assessment and measurements, preliminary project preparation, building permit deocumentation, construction documentation, engineering services, author supervision
Construction expenses
approx. 6,000 mill. CZK / 222 mill. EUR

TECHNICAL DETAILS
built-up volume: c. 500 000 m3
built-up area: 12 000 m2

TYPICAL UNITS
number of beds: 600

Reconstruction of the complex, which is one of the largest projects in the company OBERMEYER HELIKA, started in 2003 with the development of a general plan of the whole area. It touched on a complex set of pediatric fields including oncology, comprehensive outpatient services and a childhood injury center. The reconstruction of other parts of the hospital was also solved. Twelve operating theaters and a diagnostic center equipped with a CT scanner and a tomograph are available in the reconstructed hospital.