THOMAYER HOSPITAL, SURGICAL UNIT RECONSTRUCTION, PRAGUE

Customer
Fakultní Thomayerova nemocnice s Poliklinikou
Architect
OBERMEYER HELIKA a.s.
Construction Period
Project realisation
2010 - 2011
Activities undertaken
building permit documentation, contractor selection documentation, construction documentation, author supervision
Construction expenses

TECHNICAL DETAILS
B1 - reconstructed operating theatres, ICU and facilities : 1 702,0 m2 : 1 700 m2
technical area: 350 m2
B4 - reconstructed operating theatres, ICU and facilities : 1 702,0 m2 : 680 m2
technical area: 360 m2

During the reconstruction of the pavilion B1 FTNsP were in the area of the original operating rooms on the 1st floor built construction of three new operating theatres equipped with modern surgical and imaging technology. Among the new dispositions are adjacent spaces - pantries patients sterilization, operating room nurses, changing filters for doctors and mainframe staff and so on.

In building the pavilion B1 wing created space intensive care unit with a new technical backgrounds. The renovated space underground floor will house the HVAC, LV substation, compressor station and engine vacuum. On the roof above the operating rooms will house the cooling.

In the newly renovated pavilion B4 are two operating theaters for urology and two halls for the department of children's trauma centers, including service rooms, sterilization, changing rooms etc. including new technical facilities.

Hide
Informace Další Předchozí Zavřít